Activity Date Project Launch 12/14/09 IOC Start 12/14/09 IOC End 01/13/10 Survey Ops Start 01/14/10 Post-Launch Assessment Rev. 01/26/10 Survey Ops Midpoint 05/28/10 Survey Ops End 10/13/10 Prelim. Release Review 03/08/11 Prelim. Release Approval 03/29/11 Prelim. Release 04/12/11 Final Release Review 02/16/12 Final Release Approval 03/01/12 Final Release 03/13/12 Provisional Processing 01/20/10-03/09/10 (using v3.2+) First Pass Processing 03/10/10-12/07/10 (using v3.5) Prelim. Release FPG 06/29/10-12/23/10 Prelim. Relase Valid. 01/03/11-04/12/11 Second Pass Processing Readiness Review 03/03/11 Second Pass Processing 03/10/11-07/15/11 (using v4.0) Final Release FPG 07/18/11-10/05/11 Final Release Valid. 10/06/11-03/13/12 User Support 04/12/11-09/21/12 Doc. Final, IRSA Hand-Off 03/14/12-09/21/12